When a wall comes out during load bearing wall removal, the load it was carrying has to go somewhere, into a beam. The two most common options in Toronto renovations are steel (a W-beam) and LVL (laminated veneer lumber). Neither is universally "better," the right choice depends on span, load, and ceiling clearance.
What Is a Steel Beam
A solid steel W-shaped beam offers the highest strength-to-size ratio of the common beam options, which is why it's typically specified for longer spans or heavier loads, such as a wall also carrying a second storey or significant roof load. Not sure whether your wall is structural? See how to tell if a wall is load bearing.
What Is an LVL Beam
Engineered lumber made of thin wood veneers bonded together under pressure, LVL is a genuinely strong structural material, more affordable than steel for shorter to mid-length spans, and generally easier to work with on site since it doesn't require the same lifting equipment or welding.
Span Capacity Comparison
Steel generally spans farther per unit of depth than LVL. To match steel's capacity over the same span, LVL sometimes needs to be sized deeper, or multiple LVL plies bolted together, which can affect both cost and ceiling clearance.
Cost Comparison
Steel typically costs more per linear foot once fabrication and installation are factored in. LVL is often more budget-friendly for shorter spans, but the cost gap narrows on longer spans that require multiple LVL plies to achieve the needed capacity.
Ceiling Clearance Impact
Steel beams can often be sized shallower than an LVL beam carrying the same load, which helps preserve ceiling height in the finished space. Whether the beam is ultimately boxed in or left exposed as a design feature affects the finished look either way, independent of which material was used.
Installation Considerations
Steel beams require crane or manual rigging to lift into place, and sometimes welding or bolted connections at each end. LVL is significantly lighter and easier to maneuver on site, though it may require multiple plies bolted together during installation to reach the required capacity.
| Factor | Steel | LVL |
|---|---|---|
| Strength-to-size ratio | Highest | Strong, but needs more depth for equivalent span |
| Typical cost | Higher per linear foot | More budget-friendly for shorter spans |
| Ceiling clearance | Can often be shallower | May need more depth for equivalent load |
| Installation | Requires rigging, sometimes welding | Lighter, easier to maneuver, may need multiple plies |
Which One Your Engineer Will Likely Recommend
The final choice comes down to the calculated load, the span, and the existing ceiling height, not a matter of homeowner preference alone. Learn more about how this fits into the broader load bearing wall removal process and where beam selection happens in that sequence.
A useful way to think about it: steel and LVL aren't competing products, they're two tools an engineer chooses between based on the specific structural math for your wall. Trust the calculation, not a general preference for one material over the other.
What the Engineer Looks At When Choosing
The material is the last decision in a sequence of calculations, not the first. Before an engineer picks steel or LVL, several inputs have to be established, and each one can push the answer in either direction.
- The span. How far the beam has to reach between its supports. Longer spans demand stiffer, deeper or stronger members.
- What the beam carries. A wall that supports only a roof is very different from one that supports a second storey, a bathroom with heavy fixtures, or a concentrated load from a post above.
- Deflection. A beam can be strong enough not to fail and still sag visibly or crack the finishes above it, so the engineer also checks how much it will bend under load.
- Bearing at the ends. The beam has to rest on posts or walls that can take its load, and the posts have to land on footings that can carry it into the ground.
- Available depth. How much room there is between the floor and the ceiling, and whether the owner wants the beam hidden in the ceiling or visible below it.
Only after those are known does the material choice come into view, and often the answer is obvious. A modest span with a roof load tends to suit LVL, while a long span carrying two floors tends to suit steel. The engineer's job is to find the option that does the work in the space available.
Costs Beyond the Beam Itself
When people compare steel and LVL they usually compare the price of the beam. In practice the beam is one line in a longer list, and the other lines can differ between the two materials.
A steel beam needs to be lifted into place, which can require rigging or a small crane, and it is connected with welded or bolted plates. It also needs a protective coating and, if it is going to be boxed in, a way to fasten the finish to it. LVL is lighter and goes in with ordinary tools, but if the load requires several plies they have to be fastened together exactly as the engineer specifies, and the beam must be protected from moisture and kept dry. Neither material is exempt from the supporting costs: the posts, the footings underneath them, the temporary shoring, the engineer's fee and the inspection are part of every project.
That is why the cheapest beam does not always produce the cheapest project. A shallower steel beam that avoids relocating a duct or lowering a ceiling can save money elsewhere, while a deeper LVL that fits without any change may cost less overall. Our load bearing wall removal cost guide shows how these items appear on a real quote.
Exposed or Boxed In: How the Finish Changes the Choice
How you want the beam to look is a fair input, even though it will not override the engineering. There are three common approaches.
Boxed in. The beam is hidden behind drywall in a slightly lowered section of ceiling called a bulkhead. This is the most common finish, because it blends into the room, and it is where a shallower steel beam has an advantage, since the bulkhead can be smaller.
Exposed. The beam is left visible as a feature. A steel beam can be painted for a clean, industrial look, while an LVL beam can be finished to show the wood. Either way, the detail work matters, because everything about an exposed beam is on display, including how it meets the walls and posts.
Recessed. In some layouts the beam can be placed within the depth of the floor structure above so it does not hang below the ceiling at all. This keeps the room clean but requires careful engineering of the floor connections and often a deeper or stronger beam, so it is a decision for the engineer and not a finish choice alone.
Whichever you prefer, tell your contractor and engineer early. It is much easier to design for a finish than to adapt to one after the beam is ordered.
Three Illustrative Scenarios
These examples are simplified, but they show how the same two materials can be the right answer in different situations.
A short opening between a kitchen and dining room
A single-storey wall carrying only the roof, with a modest span. Here LVL is often the practical choice: it is strong enough, easier to install, and usually more affordable, and the extra depth is easy to hide in the ceiling.
A long open-concept span under a second storey
A wall that also carries the floor above, with a long span. The load and the span both argue for steel, and a shallower steel beam may be the only way to keep the ceiling height you want without a large drop.
A wall removal combined with basement work
When the project also involves the basement, the posts that carry the new beam land on the foundation, so the footings below are part of the design. Our guide to combining wall removal with basement underpinning explains how the two fit together. In any of these cases, the engineer decides, and your preferences about cost, ceiling height and finish are the inputs to that decision.
Frequently Asked Questions
Steel has a higher strength-to-size ratio, meaning it can carry more load for a given depth of beam, but LVL is still a genuinely strong structural material for shorter to mid-length spans. "Stronger" isn't really the right framing, it's about matching the right material to the specific span and load.
The engineer's calculations determine what's structurally required for your specific span, load, and ceiling clearance, which narrows or determines the choice. You can express a preference, particularly around ceiling clearance or budget, but the final selection needs to meet the engineered requirement.
It can. A shallower steel beam may allow for a less noticeable ceiling drop if left boxed in, while a deeper LVL beam sized for the same span might require a more visible soffit. Both can also be left exposed as a design feature rather than boxed in, which changes the visual impact either way.
Yes, though steel and LVL cover the vast majority of residential load bearing wall removal projects in Toronto. Other engineered wood products like PSL (parallel strand lumber) or glulam exist for specific applications, but your structural engineer would only specify these if your project's requirements called for it.
Steel in a dry interior is protected with a primer or paint, and that is usually enough. If the beam is going to be boxed in, the finish is mostly cosmetic, while an exposed beam is finished to suit the room. Moisture is the main concern, so the engineer and contractor will take extra care if the beam is near a damp area.
No. Both steel and LVL need stamped engineering drawings, a building permit and a framing inspection before the beam is covered. The material is specified in the drawings, and the inspector checks that what was installed matches them.